31st October 2018

? HAPPY HALLOWEEN ?

  • We can all agree, the year is absolutely flying, November already!
  • The project is going well, the roof slab is poured and we are well into the internal fit-out stage
  • Tilers started on site this week on level 1
  • Plasterers are framing on level 4 and sheeting on level 3
  • Cabinetry starts tomorrow
  • We are still aiming for Mid-Feb completion