? HAPPY HALLOWEEN ?
- We can all agree, the year is absolutely flying, November already!
- The project is going well, the roof slab is poured and we are well into the internal fit-out stage
- Tilers started on site this week on level 1
- Plasterers are framing on level 4 and sheeting on level 3
- Cabinetry starts tomorrow
- We are still aiming for Mid-Feb completion